CARNIVAL PHASE 2 DELIVERY AND PROGRAMME

KEY DATES 

This table will be updated with key dates to reflect the most up-to-date programme

 

Action

Date

Planning consent granted (O/2015/1056)

05 August 2015  

Library Offer public consultation  

Spring 2016

Leisure Strategy public consultation

Winter 2016

Leisure contract procurement  

Ongoing, with appointment expected in 2018

Detailed design work  

Ongoing

Phase 2 Public engagement

Friday 28 April to Sunday 21 May (ENGAGEMENT NOW CLOSED)

Drop in public exhibitions (an opportunity to meet the team, find out more about the proposals and ask questions)

Monday 8 May 4pm to 7pm at Wokingham Library

Tuesday 16 May 4pm to 7pm at Carnival Pool Leisure Centre 

Submission of detailed planning application (application number 172012)

20 July 2017 (NOW SUBMITTED)

Statutory Planning Consultation period

20 July - 15 September 2017 (NOW OPEN)

Planning Committee date  

Autumn - Winter 2017 (date tbc)  

Start work on site  

late 2019 to mid 2021

Phase 2 works completed

Mid 2021 

New library and leisure centre opens

Mid 2021

MAIN WORKS

In July 2015 the council secured detailed planning consent for Carnival Phase 1 and outline planning consent for Phase 2.

Since then further work has been going on to look in detail at the existing facility and talk more to local service users about the types of leisure and community facilities needed across the borough and where these should be located. This included consultation on a new Leisure Strategy and Library Offer.

Feedback from the public engagement on the Phase 2 proposals was used to help inform the planning application and will help guide further discussions around the detailed designs and layout of the library and public areas.  

A detailed planning application was submitted in summer 2017.  

 