Peach Place Delivery and Programme

Key Dates

This table continues to be updated with key dates as the detailed programme progresses

 

Action  

Date 

Planning Consent granted (F/2014/2637)

5 March 2015

Bush Walk Maintenance and Repair Works     

Completed Summer 2016

Appointment of Dawnus Construction Ltd as main build contractor

21 November 2016

Pre-construction works and preparations for starting on site

November 2016 - 9 January 2017 (NOW ON SITE)

Handover of site to Dawnus and closure of Rose Street car park

9 January 2017 (NOW ON SITE) 

Initial site works and surveys (including stripping out of empty buildings for demolition)

January - March 2017 (NOW ON SITE)

Closure of Peach Street footpath (from the Redan to the former Clinton's unit)  

13 February 2017 - March 2018 (FOOTPATH NOW CLOSED)

Restrictions on Rose Street footpath and lane adjacent to site (two way vehicle access maintained throughout)

13 February 2017 - September 2018 (in phases during this period) (TWO WAY TRAFFIC MAINTAINED THROUGHOUT)

Temporary overnight closure of Peach Street (to allow installation of safety barriers for lane closure)

10pm Sunday 26 February until 6am Monday 27 February (road will reopen on Monday 27 as single lane)  (COMPLETED)

Closure of single lane of Peach Street (from the Redan to the former Clinton's unit)  

27 February 2017 - early June 2017 (expected 15 week closure) (ROAD REOPENED)  

Closure of Luckley Path (to allow for improved vehicle flow on Peach Street and safer pedestrian access whilst other footpath is closed)

27 February 2017 - March 2018 (reopening date will be kept under review) (NOW CLOSED)

Erection of scaffolding and protective netting to allow for demolition

13 March 2017 (COMPLETED)

Main demolition works commence

W/C 20 March 2017 (COMPLETED)

Main construction works

March 2017 - October 2018 (NOW ON SITE)

Works to Costa and Superdrug frontages (businesses remain open at all times)

25 August 2017 - December 2017 (NOW ON SITE) 

Works to Rose Street frontages

25 August 2017 - May 2018 (NOW ON SITE)

Completion of construction

November 2018

Opening of pre-let units

For Christmas trading 2018

 

Main Works and appointment of Build Contractor

In April 2016 the Council started the process of tendering for the build contract and worked closely with the tendering companies on their approach to delivering the project on the town centre site. These discussions covered a wide range of things such as site constraints, control of noise and working practices, management of construction traffic, continued servicing of businesses remaining on site, and how to manage and minimise the length of the demolition phase which requires a temporary single lane closure of Peach Street due to the close proximity of the buildings to the highways.     

In January 2017 main work started to deliver the Peach Place proposals.

This work includes the closure of the Rose Street car park, demolition of existing buildings on site, and development of new shops, homes and a public square.  

Dawnus Construction Ltd has been appointed as main build contractor. Details of their ongoing programme are shown above, and will be updated with detail over the coming months as the project moves forward to keep people updated with what is happening.

 

 